Back Main Menu Next


 

Bourne Stream Partnership

PUBLIC CONSULTATION ON 

HABITAT ENHANCEMENT OPTIONS FOR COY POND GARDENS

1.0     Objective

To find out the views of the local community on the four options for habitat enhancement work in Coy Pond Gardens to help determine the way forward for this development

 

2.0     Background

The Bourne Stream is a typical urban watercourse and is prone to periods of poor water quality following rainfall events, particularly after dry summer conditions.  The resultant “first flush” from surface water drains leads to bacterial contamination of the stream and the bathing beach at Bournemouth Pier.  This can lead to the failure of the Bathing Water Directive Guideline standards.

 

To investigate ways to improve stream water quality the Environment Agency contracted Peter Brett Associates to produce a scoping study for incorporating surface water run-off best management practices (BMPs) in the catchment (Peter Brett Associates, 1999).  This report put forward possible in-stream features, such as ponds and infiltration ditches to increase retention times and provide treatment to improve water quality.

 

To take forward this work a partnership of local public and private organisations has been formed.  This partnership has agreed a strategy (Bourne Stream Partnership, 2000) for the catchment that includes the promotion of source protection and in-stream SUDS to improve water quality, habitat and biodiversity.

 

In October 2001, Peter Brett Associates produced a feasibility study (Peter Brett Associates, 2001) to identify options for habitat enhancement work in Coy Pond Gardens, one of the areas highlighted in the 1999 report.  The four options were:

Option 1 – in-stream pond at the top end of the gardens

Option 2 – meanders at various locations along the stream course

Option 3 – in-stream pond above Coy Pond outlet

Option 4 – braided stream downstream of Coy Pond outlet

This report summarises the public consultation on these four options.

 

In addition, another option, based on Option 1, proposed by a local resident was considered by Peter Brett Associates (Peter Brett Associates, 2002), although this did not form part of the formal public consultation.

 

3.0     Method

The public consultation was held in St. Johns Church, Surrey Road on Thursday 23rd May 2002 between 7 and 9pm, and on Friday 24th May 2002 between 9 and 12pm.  A flyer advertising the event was distributed by the Friends of Coy Pond to local residents.  In addition, two press releases were issued before and after the event and there were three press articles on the event.

The detail of the four options was depicted on 10 display panels and was augmented by a computer simulation of the options that allowed members of the public to see what the schemes would look like on the ground.

A questionnaire and comments book were used to capture the views of the public.  Following the event, a leaflet depicting the options was produced to provide an opportunity for those residents who could not attend the display to comment on the options.

Above:  Neil Smith of the Environment Agency explains the in-stream options presented to the community, May 2002

 

4.0     Results

i)  The number of people who attended the sessions was not recorded.

ii)  The results from the questionnaires are shown in Tables 1, 2 & 3, Figure 1.

iii)  88 questionnaires were completed, of which 60% visited the gardens on a daily basis and lived within one or two roads of the Gardens (See Table 1).

iv)  The majority of respondents (85%) supported a change in the Gardens (See Figure 1), with most (51%) supporting Option 1, an in-stream pond at the top of the Gardens (See Table 2).  Overall, the in-stream meanders (Option 2), is the next preferred option (See Table 2).

v)  The main concern was proper long-term maintenance of the schemes as shown in Table 3 and mentioned in the comments book.

 

Table 1 : Answer to question 1

How often do you visit Coy Pond gardens?

 

Number

Percentage

Daily

53

60.2

Weekly

19

21.6

Twice a Month

6

6.8

Less than once a month

9

10.2

Holiday

0

0

No answer

1

1.1

Total

88

100

 

 

Figure 1: Answer to Question 2

In principle, do you support a change to the Gardens?

 

Reasons why answered ‘no’ to Question 2

1.   Proposals add to problems

2.   Waste of money

3.   Change Bournemouth not Poole

4.   Money should be spent on Coy Pond (x2)

5.   Dredging should be done instead (x3)

6.   Reed beds may be eyesores

7.   Proper maintenance is not likely to be carried out (x2)

8.   The space should be kept for recreation

9.   Do we really need it?

10. None of the proposals will have an effect

11. Pollution should be removed at source

12. Gardens are not the problem.  Need to spend real money to sort out problem


Table 2 : Responses to Question 3

If you do support a change, please rank the options in order of preference

 

 

 

1st choice

2nd choice

3rd choice

4th choice

Totals

Option 1 –

pond at top end of gardens

42

11

13

13

79

Option 2 –

in-stream meanders

14

19

15

10

58

Option 3 –

pond in middle section of gardens

11

21

9

10

51

Option 4 –

braided stream d/s of Coy Pond outlet

14

11

12

17

54

 

Totals  

81

62

49

50

 

 

Notes:

Only 39 questionnaires had question 3 answered correctly, 7 were not filled in at all and 40 were filled in but not correctly.

 

Table 3: Responses to open question 4

 

5.0     Discussion

This was a successful event and, although the actual number of people attending was not recorded, 88 questionnaires were completed by people living by and visiting the Gardens.  This success was mainly due to the existence and involvement of the local Friends of Coy Pond Group, together with the use of a local venue and good press coverage.  The leaflet, whilst providing a useful hand-out, did not stimulate any further responses from local residents.

 

The partnership is happy to proceed with proposals for the Gardens as the majority of local residents supported some form of development in the Gardens.  The preferred option is the development of a pond at the top end of the gardens (Option 1) and this will take into account the additional proposal reviewed by Peter Brett Associates (Peter Brett Associates, 2002).  The Partnership will also support the development of in-stream meanders as overall this was the second preferred option and has the best cost/benefit ratio for habitat enhancement (Peter Brett Associates, 2001).

 

The Partnership has taken note of the comments made by the respondents and in particular will ensure there is a management plan in place for the future maintenance of the development in the gardens.

 

It is worth pointing out the Partnership is also undertaking other work in the catchment to complement this in-stream habitat enhancement work.

 

6.0     Recommendations

i)  To design and construct in-stream habitat features in Coy Pond Gardens to enhance the stream for the local community and wildlife.

ii)  To produce an agreed management plan before proceeding with the development to ensure long-term maintenance of the features is addressed.

7.0     References

Bourne Stream Partnership (2000) Bourne Stream Strategy

Peter Brett Associates (1999) Scoping Study for Surface Water Run-off BMPs in the Bourne Stream Catchment

Peter Brett Associates (2001) Feasibility Study. Bourne Stream Coy Pond Gardens

Peter Brett Associates (2002) Bourne Stream Coy Pond Gardens.  Comment on Proposals by P Jones Esq.


Back Main Menu Next


© 2003-2008 Bourne Stream Partnership : last updated 26/01/2008

 

Disclaimer and copyright

Stats 2004-07: 184,964 visitors